decrease resource amount in resource pool

1 view (last 30 days)
大家好
hello everyone
Please answer to me, how can I decrease resource amount in resource pool via signal port?
increase is not problem , with message.data = x, i can increase on x items.
but how about decrease.
thanx a lot
  1 Comment
Joep Eijkenduijn
Joep Eijkenduijn on 13 Apr 2021
Hi Ivan,
I don't know how to decrease the amount of resources. Documentations say it is not possible. But I have found a simple workaround:
Build the following system outside of your main system:
Entity generator: 1/s
First server: server time, you put the time point at which the decrement in resources must happen. Server capacity = infinite.
Resource acquirer: acquire the amount of resources by which you want it to decrease.
Second server: Server time, long enough that it will keep the entity during the entire simulation. Capacity = 1.
And last a terminator.
This system holds the resources during the simulation which in practice seems like a decrease. Hope this helps.

Sign in to comment.

Answers (0)

Categories

Find more on Application Deployment in Help Center and File Exchange

Products


Release

R2020a

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!