Baseline criteria in Test Manager: Is there any method to recapture the baseline criteria and replace the .mat file?
1 view (last 30 days)
Show older comments
I am having more than 100 test cases for a model. When I make any changes to the main model the baseline criteria has to be replaced. Is there any method for replacing the baseline criteria if multiple test cases are available?
0 Comments
Answers (1)
Rong Mi
on 8 Aug 2018
You can try to create 100 iterations instead of having 100 test cases for one model. So in each iteration, you can add a corresponding baseline file for it.